Update #9

With the final rock being placed on the reclamation face earlier this week that means that site works are now complete.  Preliminary reporting indicates that the project has been successful and the remedial targets have been achieved.  The final volume dredged was 32,516m3, and the northern extent of the reclamation is as it was planned.  Heron are underway with disestablishing their plant and equipment and restoring the site.  Once they have left we will commence cement stabilisation of the reclamation and final paving.

Kelly Leonard