Update #5

The previous fortnight has been focused on commissioning the mixing plant and completing the pilot trial.  The key outcome of the pilot trial was for the mudcrete blend specification to be delivered at project scale.  The first batches of mudcrete to be processed in the mixing plant look very favourable and it is consistent, well mixed and curing well.  The pilot trial also gave us the opportunity to test all of the equipment and systems for the project.  It has revealed one or two commissioning challenges which we’re able to remedy prior to the project commencing at full scale.  The early part of next week will see the project team stand down while we wait for the mudcrete analysis to be completed. Dredging and reclamation construction at project scale will be starting early in December.

Kelly Leonard