Update #6

After a well earned Christmas break Heron are back onsite and in full production, and overall progress continues to be pleasing.

Read More
Kelly Leonard
Update #5

The previous fortnight has been focused on commissioning the mixing plant and completing the pilot trial.  The key outcome of the pilot trial was for the mudcrete blend specification to be delivered at project scale.

Read More
Kelly Leonard
Update #4

The finishing touches are underway to complete the project site construction, and the crew have worked in some challenging weather conditions this week to finish this.  The last pieces of the pugmill are currently going together, meaning the setup of equipment on Kingsford Quay East is almost complete, including all of the necessary environmental controls. 

Read More
Kelly Leonard
Update #3

The project is progressing well as Heron continue to establish onsite at the Calwell Slipway.  The plant and equipment necessary for this project is arriving on site in a steady stream.

Read More
Kelly Leonard
Update #2

Heron have arrived onsite and begun their site establishment.  Some of their plant and equipment for this project was already here, and has been laying up at the Calwell Slipway.

Read More
Kelly Leonard
Update #1

Welcome to the website for the Calwell Slipway Remediation Project.  Currently ranked number 2 on The Ministry for the Environments (MfE) Contaminated Sites Remediation Fund Priority list the Calwell Slipway has the unenviable position of being one of New Zealand’s most contaminated sites

Read More
HotHouse