Calwell Slipway Remediation Project
 
 
slip-map.jpg
 
This project will remove and stabilise contaminated marine sediments from the Calwell Slipway Basin, preventing them migrating to other areas of Nelson Haven.  It will restore navigability to the Calwell Slipway Basin to ensure the future operability of businesses reliant on access to the Basin in the Marine Engineering Hub for Nelson.
 
 
 
 

Project Timeline

May '16 -
Jan 17

Gain Resource
Consents for
the project

May '16 -
MAY '17

Procure
Specialist
Services

Oct '17 -
Nov '17

Site
Establishment

Nov '17 -
Mar '18

Dredging and
reclamation
construction

mar '18 -
apr '18

Demobilisation,
site restoration
and project
closure

 
 
 
 

Live Project data

 

project time lapse

 

Latest news

Contact Us

Kelly Leonard
Project Manager

Direct dial: +64 3 539 3861
kelly.leonard@portnelson.co.nz